← All rankings

36 · Nuclear · SMR developers

SMR developers: China

PERIOD · 2026 · STATUS AT NOVEMBER 2026

DEFINITION

Ranked by stage reached — operation, construction, design

Developers are ranked by the furthest stage reached by their flagship small modular reactor — a unit of 300 MWe or less: commercial operation first, then construction, then design stage, with design-stage entries ordered by design maturity — detailed design, then preliminary design, then concept design. Capacities are the developers’ own published figures, or the IAEA SMR Catalogue 2024 figure where a developer’s own figure is ambiguous. Developers with a named design and a published capacity are ranked by stage; named entrants whose capacity is undisclosed — or whose existence rests on a single unverified mention — are still listed, at the foot of the table and labelled as such, as are ranked developers’ second designs, which are listed unranked with remarks.

210 MWeHTR-PM — the only SMR in commercial operation
125 MWeACP100 — the only SMR under construction
11Entries listed, incl. second designs & unverified entries
RankDeveloperFlagship design · stage reached
1China Huaneng (华能集团)ChinaHTR-PM · 210MWe — in commercial operation since Dec 2023 (Shidaowan, Shandong)
2CNNC (中国核工业集团)ChinaACP100 Linglong One · 125MWe — under construction, in commissioning (Changjiang, Hainan)
3SPIC (国家电力投资集团)ChinaHAPPY200 · 200MWt — design stage (detailed design); heat only, no power output
4CGN (中国广核集团)ChinaACPR50S · 200MWt / ~60MWe — design stage (preliminary design); no construction start announced
5Junhe Atomic (钧合原子)ChinaJunhe One · ~100MWe — design stage (concept design completed, company-disclosed); demonstration project targeted within 3–5 years
6Fenglin Nuclear (凤麟核)ChinaHedianbao (CLEAR-M10d) · 14MWe — design stage (conceptual design; engineering simulation prototype built); 35 MWt lead-cooled microreactor, figures developer-reported
7Azure Fulcrum (蔚蓝支点)ChinaWeilan One (WL-100) — design stage (first-generation design in progress); capacity not published by the developer — no figures shown
—Weihe Xingneng (微核星能)ChinaHeat-pipe microreactor — NOT VERIFIED: known only from a single investor-media mention; no legal entity, named design or capacity could be confirmed
—CNNC (中国核工业集团)China · second designACP25S — marine reactor in the ACP family, named in official sources; no capacity published — listed with remark, not ranked
—SPIC (国家电力投资集团)China · second designHemei One — integral heating reactor tied to a Haiyang demonstration project; no capacity published — listed with remark, not ranked
—CGN (中国广核集团)China · second designHuakun One — floating-reactor demonstration project; its site-selection review opinion, issued by the nuclear safety regulator in November 2026, is the furthest regulatory step reached by any CGN small reactor — but no capacity published, so listed with remark, not ranked

Reading the table: CNNC runs the widest programme — beyond the ACP100 it fields a marine version (ACP100S, basic design) and the 400 MWt Yanlong (DHR-400) heating reactor, both at design stage; its 660 MWe HTR-PM600 unit at Xuwei, whose construction started in November 2026, is a multi-module scale-up above the SMR class and is not counted here. The HTR-PM is catalogued as an SMR by the IAEA; its 210 MWe is the catalogue figure (the operator’s gross figure is 211 MWe). The lowest entries are the sector’s private developers: Junhe Atomic, founded in 2025 by Tian Jiashu — a former deputy chief engineer of both CNNC and CGN who once chaired the Linglong One development company — Fenglin Nuclear, a CAS spin-out, and Azure Fulcrum, whose first-generation design is still in progress and whose capacities are undisclosed. Checked and not ranked: CSSC’s 719 Institute completed preliminary design of the HHP25 marine reactor (100 MWt / 25 MWe), but it is a naval research institute rather than an enterprise developer, and no programme activity has been verified since about 2019; Sichuan Energy Nuclear Industry, a provincial-SOE/NPIC joint venture unveiled in October 2026, has announced a 1–10 MWe microreactor programme but no named design.

Withheld

Per-company SMR revenue, orders and programme spending: not published — not shown. A November 2026 census of private developers found no other publicly identifiable fission-SMR startup beyond the entries on this page: the ‘20-plus SMR startups’ figure quoted in Chinese media is an industry estimate, and the remaining projects tracked by investors are undisclosed.