China's AI Power Crunch, in Primary Sources

Ask how China will power its AI build-out and most English-language answers start with chips. The Chinese policy documents start somewhere else: with where the load is allowed to sit, what efficiency it must prove, and how much of its electricity must be green. That was the conclusion of our earlier short card on this page — datacenter load is a grid problem now, not a chip problem — and this note is its full expansion, rebuilt entirely from the primary texts: the 东数西算 "East Data, West Computing" layout plans, the 2024 data-centre green action plan, and the new-power-system plan that carries the transmission half of the answer. Interconnection queues, transformer lead times and behind-the-meter generation decide where the next gigawatt of AI capacity can land in any country; in China, those constraints are not just market facts — they are written into approval rules a foreign reader can check. Every number below is either one of the six verified NEA figures in our Data section or a target quoted from an official document named in the sources, with its Chinese title, issuing bodies and date. Where a figure in wide circulation could not be traced to a primary text, this note says so and leaves it out.

8 + 10National computing hubs and data-centre clusters fixed by the layout — four hubs in the east, four in the energy-rich west
≤1.2 PUECeiling on power usage effectiveness for data-centre projects inside national hub nodes, end-2025 target in the 2024 green action plan
>80% green electricity share required of newly built data centres in national hub nodes by end-2025 — set in the Dec 2023 opinion, repeated in the Jul 2024 plan

01 · THE QUESTIONTwo mismatches, and the two moves that answer them

China's computing demand is concentrated where its people and industry are — the east. Its cheapest, cleanest generation increasingly sits in the west and north: the wind and solar bases behind the verified end-2025 totals in our Data section (1,200 GW of solar and 640 GW of wind installed, within a 3,890 GW national system). AI training and inference widen that geographic gap every year, because a single large cluster is a power-plant-scale load that cannot be served by wishing local capacity into existence.

Beijing's documents answer with two moves run in parallel. Move the compute to the power: steer new data-centre capacity toward western hubs where renewable energy, land and cool climates are abundant — the 东数西算 programme, literally "eastern data, western computing". Move the power to the compute: keep building the west-to-east transmission arteries — 特高压 UHV (ultra-high voltage) lines under the 西电东送 west-to-east power transmission programme — so eastern load centres, including the data centres that must stay east for latency, can draw on western generation. Everything else in this note — the hub map, the PUE ceilings, the green-electricity quota — is machinery for making those two moves happen in the right order.

02 · THE LAYOUT东数西算: eight hubs, ten clusters, a written division of labour

The framework document is the May 2021 implementation plan for computing hubs in the national integrated big-data-centre system (《全国一体化大数据中心协同创新体系算力枢纽实施方案》, NDRC and partner agencies). In February 2022 the NDRC, the Cyberspace Administration, the MIIT and the NEA jointly approved the build-out, and the layout has been fixed since: eight national computing hubs — Beijing–Tianjin–Hebei 京津冀, the Yangtze River Delta 长三角, the Greater Bay Area 粤港澳大湾区 and Chengdu–Chongqing 成渝 in the east; Inner Mongolia 内蒙古, Guizhou 贵州, Gansu 甘肃 and Ningxia 宁夏 in the west — containing ten national data-centre clusters where large facilities are meant to concentrate.

The 2021 plan sorts the country by function, and the sorting is the policy. The four eastern hubs, where user scale and application demand are strongest, are to deploy capacity intensively under tight land, energy and water constraints, close to the demand they serve. The four western hubs are designated rich in renewable energy and suited by climate; their assigned role is to take the work that does not need to be near the user — background processing, offline analysis, storage and backup — as a national non-real-time computing base. Latency-sensitive work (the plan's own examples run to finance, industrial internet and AI inference serving eastern users) stays east; latency-tolerant training, rendering and archiving is pushed west. Read the hub map as a latency budget written into geography.

Later documents put numbers on the steering. The December 2023 opinion on deepening the programme (《关于深入实施"东数西算"工程加快构建全国一体化算力网的实施意见》, 发改数据〔2023〕1779号, NDRC with four partner agencies) targets, by end-2025: hub-node regions accounting for more than 60% of all new computing capacity added nationally, hub utilisation clearly above the national average, and — the figure section 04 returns to — a green-electricity share above 80% for newly built hub-node data centres. The July 2024 green action plan then hardens the layout from guidance into gatekeeping: new large and super-large data centres should be sited as a priority inside the hub clusters; large wind and solar bases are to be planned in coordination with the hubs; non-real-time facilities are supported in migrating west; and a city whose data centres older than a year sit at an overall rack utilisation below 50% may in principle plan no new clusters and no new large or super-large projects at all. Siting in China is therefore not a pure real-estate decision: the national layout is a condition of approval.

03 · THE WIRE特高压 UHV and 西电东送: the power moves east so some compute can stay

Not every workload can go west, so the second move is electrical. 西电东送 west-to-east power transmission is the decades-old programme that carries western hydro, wind and solar to eastern load centres, and its long-distance arteries are 特高压 UHV lines — the ±800 kV-and-above DC and 1,000 kV AC corridors that move bulk power across provinces with losses low enough to make the arbitrage work. The document our earlier card anchored to, the 《加快构建新型电力系统行动方案(2024—2027年)》 Action Plan for Accelerating the Construction of a New-Type Power System (NDRC · NEA · National Data Administration, Aug 2024), makes this one of its nine campaigns: a dedicated push on 大规模高比例新能源外送 large-scale, high-share renewable-energy outbound delivery — in plain terms, more and better-used corridors out of the western renewable bases, alongside the grid-stability and distribution campaigns a data-centre developer ultimately depends on.

For a reader siting load, the practical meaning is that "east versus west" is not binary. A latency-bound facility in an eastern hub is still, in the plan's logic, a claim on western electrons delivered by UHV; a training facility in a western hub is a claim on the same electrons consumed before they travel. The 2024 data-centre plan names the intended end-state 算力电力双向协同 two-way computing–electricity coordination: compute planned with the grid, and the grid planned with compute, with a first working mechanism targeted for end-2025. One honesty note, in this site's usual form: corridor-by-corridor UHV capacity figures and west-to-east transfer totals circulate widely in English coverage, but we have not yet reconciled them line by line with a primary NEA or NDRC release text, so this note cites no UHV capacity number — that point stands as 待核实 not yet verified, and the qualitative account above rests only on the documents listed below.

04 · THE RULESPUE ceilings and the 80% green rule, in the documents' own numbers

Efficiency first. 电能利用效率 — PUE, total facility energy divided by IT energy — is the metric Chinese approvals actually use, and the July 2024 《数据中心绿色低碳发展专项行动计划》 Special Action Plan for the Green and Low-Carbon Development of Data Centres (发改环资〔2024〕970号; NDRC, MIIT, NEA and the National Data Administration) states its end-2025 targets without ambiguity:

  • National average PUE below 1.5 by end-2025, with overall rack utilisation of at least 60% and renewable-energy utilisation rising an average of 10% per year.
  • New and expanded large and super-large data centres: PUE at or below 1.25 by end-2025 — and data-centre projects inside national hub nodes: PUE no higher than 1.2. The earlier four-agency plan of December 2021 (发改高技〔2021〕1742号) had set the corresponding bar at below 1.3 nationally and below 1.25 at hub nodes; the 2024 plan is a tightening, not a restatement, and project teams quoting the 2021 numbers are working from a superseded ladder.
  • Servers are specified, not just buildings. New and expanded projects must use servers meeting the efficiency levels of GB 43630-2023 (the server energy-efficiency limits and grades standard) or better — a point equipment vendors should read together with our Standards guide.

Green electricity second. 绿电 green electricity in these documents means renewable power procured and accounted as such — through green power trading 绿电交易 and green certificates 绿证, the official proof of renewable consumption — rather than a claim about the average grid mix at the socket. The rule, stated in the December 2023 opinion and repeated in the July 2024 plan, is that newly built data centres in national hub nodes exceed 80% green electricity by end-2025, inside the computing–electricity coordination mechanism above. The 2024 plan also writes the procurement into the approval itself: a new or expanded project's renewable-energy utilisation target and plan are a required, substantive part of its 节能审查 energy-saving review; projects are encouraged to raise their renewable share year by year, to co-locate with renewable generation where firm supporting power and flexibility allow, to buy through green power and certificate trading, and — in pilot form — to take 绿电直供 direct green power supply. For intelligent-computing centres inside the national AI layout, the same plan instructs regions to expedite energy reviews and strengthen green power supply guarantees: speed and green sourcing are granted together, or not at all.

One figure this note deliberately does not give: a national total for data-centre electricity consumption. Totals attributed to official agencies circulate in press coverage, but we have not traced one to a primary statistical release we can quote line by line, so under this site's discipline it stays on the withheld list — 待核实 — rather than in the text. The targets above are policy settings from named documents, not measurements; do not cite them as outcomes.

05 · WHAT IT MEANSFor operators, buyers and vendors reading from outside China

  • Siting — read the hub map before the land market. The first questions for any new large facility are now administrative: Is the site inside a national hub cluster? What is the host city's rack utilisation (below 50% on year-old stock can freeze new large projects)? Can the project pass an energy-saving review whose required contents include a renewable plan? Western hubs offer the renewable endowment the rules reward; eastern hubs offer latency the rules protect. A site outside the hub system starts the approval conversation at a disadvantage the documents make explicit.
  • Green procurement — the 80% is a new-build hub rule, met by instruments. For a new hub-node facility, plan from day one for how the >80% green share will be evidenced: green power trading contracts, retired green certificates, co-located renewables or a direct-supply pilot. The obligation attaches to the project's reviewed plan, not to a marketing claim after energisation — procurement teams should expect the energy review file, not the ESG report, to be where compliance is judged.
  • Equipment — PUE ceilings are a technology pull. A 1.2 ceiling at hub projects cannot be met by legacy air-cooled design at scale; the 2024 plan's own technology list points where demand goes: liquid cooling 液冷 and evaporative cooling, heat-pipe and fluoropump systems, DC power distribution 直流供电, modular power and high-efficiency transformers, and servers at or above the GB 43630-2023 efficiency grades. Vendors selling into Chinese AI campuses are selling against a written efficiency ladder — bring test data against the named standards, not brochure PUE.
  • Investors — separate targets, measurements and marketing. The documents above set targets (PUE ladders, the 80% rule, the 60% hub share of new capacity). Whether outcomes matched them is a different question, answerable only from the agencies' statistical releases — the same discipline our Data section applies to the NEA's six verified end-2025 figures. A pitch that quotes the 80% target as an achieved fleet average has failed the first check this note exists to teach.

The answer, in one paragraph

China powers its AI build-out by steering new data centres into eight national computing hubs — western hubs take latency-tolerant load beside abundant renewables, eastern hubs keep latency-sensitive load supplied over UHV west-to-east corridors — and by conditioning approval on efficiency and sourcing: PUE no higher than 1.2 for hub-node projects and a green-electricity share above 80% for newly built hub-node data centres by end-2025 (发改环资〔2024〕970号; 发改数据〔2023〕1779号).

Primary sources

《数据中心绿色低碳发展专项行动计划》(发改环资〔2024〕970号)

国家发展改革委 · 工业和信息化部 · 国家能源局 · 国家数据局 (NDRC · MIIT · NEA · National Data Administration) · Jul 2024 · source of the end-2025 targets quoted in this note: national average PUE below 1.5, new large / super-large PUE ≤1.25, hub-node projects ≤1.2, rack utilisation ≥60%, renewable utilisation +10%/yr, hub regions ≥60% of national new computing additions, and green electricity above 80% for newly built hub-node data centres · full text (PDF) checked line by line for this note

《关于深入实施"东数西算"工程加快构建全国一体化算力网的实施意见》(发改数据〔2023〕1779号)

国家发展改革委等五部门 (NDRC & four partner agencies) · Dec 2023 · sets the end-2025 hub targets the 2024 plan repeats: hub regions above 60% of national new computing additions, computing–electricity coordination mechanism, green electricity above 80% for newly built hub-node data centres

《全国一体化大数据中心协同创新体系算力枢纽实施方案》(发改高技〔2021〕709号)及 2022 年 2 月枢纽批复

国家发展改革委等部门 (NDRC & partner agencies) · May 2021; approvals Feb 2022 with 中央网信办 · 工业和信息化部 · 国家能源局 (CAC · MIIT · NEA) · the eight-hub / ten-cluster layout and the east–west division of labour: eastern hubs deploy intensively near demand; Inner Mongolia, Guizhou, Gansu and Ningxia take non-real-time load on renewable endowment

《加快构建新型电力系统行动方案(2024—2027年)》

国家发展改革委 · 国家能源局 · 国家数据局 (NDRC · NEA · NDA) · Aug 2024 · checked against the official release · the new-power-system frame — including the large-scale renewable outbound-delivery campaign behind the UHV west-to-east corridors; also the primary source of this page's earlier short card on datacenter load, whose conclusion this note retains

《贯彻落实碳达峰碳中和目标要求推动数据中心和5G等新型基础设施绿色高质量发展实施方案》(发改高技〔2021〕1742号)

国家发展改革委等四部门 (NDRC & three partner agencies) · Dec 2021 · the earlier PUE ladder — new large / super-large below 1.3, hub nodes below 1.25 by 2025 — against which the 2024 plan's tightening is measured

本站 Data 区六个已核实数字

WattAnalysis Verified Data section (this page, #data) · 国家能源局《2025年全国电力工业统计数据》 (NEA, Jan 2026): total installed capacity 3,890 GW, solar 1,200 GW, wind 640 GW at end-2025 — the generation base the western hubs draw on. Not cited in this note, pending primary-text verification: a national data-centre electricity-consumption total, and corridor-level UHV / west-to-east transfer capacities